Tuesday, December 15, 2020
"Professor" Bob
Sunday, December 6, 2020
Remodeling - Carpet Fiasco
The flooring contractor would have liked to install the hardwood floors before the carpet, but due to the delays with the hardwood, they had to get the carpet installed before we moved in. They said it would only take a couple of days.
They started with the upstairs bedroom. We stopped by that evening after they completed the upstairs bedroom. The first thing we noticed is that the grain of the carpet was going perpendicular to the stairs. Then we realized that they were installing the wrong carpet. They ordered and started to install the Covington, not the Queenstown. After a quick call to the contractor, they stopped the installation.
Since this was about a week before we moved in, we were kind of in a bind. The vendor acknowledged his mistake and was willing to put in the Queenstown, however, it would take two weeks in order to get it in stock and another week to get it installed. We had a big decision to make.
We went upstairs where the carpet was already installed. We looked at it with the wall color and we were satisfied that the colors matched. We got Kevin over and asked about his concerns on the steps. There was already a step carpeted, but we did not like that the grain was perpendicular to the step. So, he came and folded it over the bullnose of the step. Apparently, our steps are a bit thicker than normal, so he was not concerned that the backing would show through when the carpet was put on the steps.
We then discussed that we did not like the way the grain was running lengthwise down the stairs. He told us that since there was a doorway at the top of the stairs, they could easily make a seam there and rotate the carpet 90 degrees. With that assurance, and the deadline coming, we decided to go with the original carpet we chose. They were able to reschedule the installers, and the carpet was in before moving day.
However, the saga does not end there. After the pile of furniture in the downstairs bedroom was moved, we discovered a lump in the floor. We called Kevin, and he came out and tried to hammer out the lump. Didn't work. Finally, the installer was called back, he pulled up the corner of the carpet and fixed the problem.
On the way out, I asked the installer what he found. He sheepishly showed me a small piece of tack strip that he left under
Remodeling - Finished Upstairs Bathroom
With the design complete, the next phase was putting everything in place. All the tile work was done by the time we moved in, but the finishing touches were late. The stone on the half wall and the shower sill couldn't be measured until the walls were complete, and the glass couldn't be measured until after the stone was installed. Needless to say, the glass didn't get installed until the week after we moved in. Too bad they installed the wrong shower door. That took a couple of more weeks to finish off.
Meanwhile, the cabinet maker had to close during COVID so the deliveries got pushed out until after we moved in. (Luckily the downstairs bath was done.) When they finally were delivered, the vanity was half-inch too wide, leading to much muttering from the contractor. They did wedge it in there, so they were ready for measuring the countertops.
They left us a small can of touch up paint for the cabinets which we foolishly left in the drawer of the cabinet. When the countertop installed the counters, the paint can was stuck in the top drawer. Not certain how the contractor got that one out, but I know the can was a bit dented when it was recovered.
The rest of the install went without a hitch, so after the mirror install at the end of July, our master bath was complete.
Saturday, December 5, 2020
Remodeling - Fireplace
The fireplace in the condo was a wood burning fireplace, which while functional, wasn't very practical. There wasn't a real good place to store firewood, so we were kind of limited to those Duraflame kind of logs. It also had this ledge kind of thing where the hearth was floating off the floor. So very 70's. At a minimum, we wanted to put some type of stone on the wall.
Remodeling - Railing
Initially, we were going to paint the railings white to match the baseboards and trim, but after we saw the wood, we decided that it would be a shame to cover it with paint. I asked the contractor if we could have the painters stain the railings, but he said that it would cost us. I told him that I would do it, but he would have to knock some money off the painter's budget.
Next, we had to decide what color of stain, if any, we wanted to use. Our first thought was to come up with a color that would match the floor. Two hardware stores and four different types of stain later, we decided that matching the floor wasn't really going to be possible. The best looking option was to just put a clear varnish on the railing.
With that decided, we put a couple of coats of varnish on the railing and it looks gorgeous.
Remodeling - Main Floor Hardwood
Our contractor recommended LeBlanc Floors, a local company. We had been looking at different hardwoods, but when we visited there, Kevin was very helpful in getting us into a birch floor with a sierra finish from Appalachian Hardwood. What we didn't anticipate is that the flooring was coming from Canada, and when the COVID shutdown hit, the factory closed. It wasn't until mid-May that they produced the flooring, which then got hung up in customs and shipping.
By that time, we had sold our house and had a move-in day of mid-June. We pressed the installers to get the flooring in before then, but unfortunately, that wasn't to be. So, we pushed him on getting the carpet installed. The downstairs bedroom was carpeted, so we decided that we'd move all the furniture that would go on the first floor into the bedroom. As you can see, it was pretty packed.The week after we moved in, the installers came in with their tools and started sanding the subfloor to smooth it out. We tried to contain it as much as we could, but there was dust everywhere. Had to live with the installation for about a week, but once they were done, it looked great.
Disclaimer: I do not get any compensation from any businesses referenced in this post.Friday, December 4, 2020
Remodeling - Finished Main Floor Bathroom
It may be hard to see in the photos, but the mirror has a grey rubber frame around it to conform to the shape of the mirror. When the contractors installed it, they removed the frame because they thought it was packing material. Luckily, we found it in the trash heap before it was taken away.
We went with oil-rubbed bronze fixtures and found some matching grab bars. Don't need them yet, but it's always a good idea to plan ahead.
Monday, June 15, 2020
What's the oldest thing in your closet?
Saturday, May 16, 2020
Media Star
I never did get any royalties from it. They did, however, keep me employed for much longer.
Friday, May 1, 2020
Remodeling - Main Floor Bathroom Design
Vanity |
Still needs some grout |
Our interior designer, Rachel, gave us a pretty nice mock up of the bathroom and suggested we put wainscoting in and use a darker color for the top part of the room. We liked the concept, although we picked a more rust like red rather than the dark blue she suggested.
Took out the toilet for painting |
The lights, mirror and plumbing fixtures are all there, waiting for the paint. The only thing left is ordering the grab bars and towel racks.
Remodeling - Upstairs Bathroom Design
Upstairs Bathroom Color Scheme |
When our contractor heard this, he recommended a flattened pebbled tile, because the ones that were naturally shaped were pretty bumpy and hard to keep clean. So, we found a 4-color pebbled flooring.
When it came to the decorative accent tile, we had hundreds to look at. We finally found one that had some of the stone from the floor, some green glass to go with the vanity, and some bluish glass. Finally, we had to pick out a base tile color, and we found an greyish/bluish/browish tile that would go well together. The photo shows the choices.
As for the bathroom floor, we decided we wanted vinyl upstairs, one because it's warmer than tile in the morning, and two, because we found a vinyl that didn't look like fake tile. It can be installed with grouting between the tiles to make it look more like a real tile. When we get around to the kitchen, we'll probably use the same brand.
Then, we had to deal with cabinets. The cabinet maker that our contractor uses is on the opposite side of Seattle, and the shut down the state the day before we were going to go pick out our cabinets. So, for a month, we had cabinets that were being ordered that we'd never seen. We had to twist the salesman's arm to get color samples sent to us so we could coordinate the rest of the material.
Laundry Side Cabinet Layout |
Finally, we dropped him a note asking when they were going to reopen, and he indicated that they'd been open for a week now. We finally exchanged some drawings with him and we've got a design that we believe will be functional.
The right hand drawer will be the ironing board, the center will be the drying rack, and the two large sliding shelves will hold laundry baskets for our dirty clothes There is room for our stacking washer/dryer to the left of the cabinets. After everything is in place, we'll probably add a hanging rod to hang clothes as well.
We still have a few details that we need to put in place, such as where towel rods need to go, but we're almost done with the decisions for that bathroom. The only thing left is the lighting.
Sneak peek at the finished product |
Remodeling - Upstairs Bathroom Rough-In
Shower Rough-in |
Future Washer/Dryer corner |
We actually sized the shower based on the vanity. Apparently, 60" is a standard size for a double vanity, so we had them put the half wall in to allow for a 60" vanity. After moving a bit of the electrical, they put the drywall back in place.
Shower boxed in |
With the drywall and floor back in, it is almost starting to look like a room again.
Sunday, April 19, 2020
Keys
Random Box of Keys |
I have no idea where most of these keys come from. I've got a better idea where some of the key rings came from, but those are lost in history as well. Some of them are labeled (like the keys to the cottage, 1500 miles away), and some are anonymous.
I wandered around the house with the keys trying the various locks on things, and I still can't find the key for a few locks. Some are now identified, but there are many that are lost in the depths of time.
Key from the house where I grew up |
Sunday, March 29, 2020
Dogs
Bailey and Zoe |
The first dog was Bailey, a Cocker Spaniel. He was conceived accidentally when one of Gail's friends left her dog in heat outside. I affectionately called him butthead. He wasn't real bright.
Gail, on the other hand, is very bright and good at training dogs. As long as she was holding treats in her hand, Bailey would do most anything. She even made him a performing dog as attested to by the entry into Maria's 4th Grade Talent Show. He was probably not the dog she would have picked, but he was a dog.
The second dog in the picture is Zoe, an Australian Shepherd rescue dog. He came about because as Bailey was getting old, I asked her if she wanted another dog. Before I knew it, she had found one and was training her as well.
Professor Henry Jones Jr, i.e., Indy |
Bailey passed away in May, 2004. Zoe in 2013. She talked me into another dog about 6 months later. Indy is an "All American Black Dog", i.e., a Lab mutt. She's trained him well, although he probably gets away with more than the other two did. You know how it is with the baby of the family.
Remodeling - Upstairs Bathroom Demo
Huge Vanity |
Didn't need that tub |
The master bathroom had an 8 foot long double sink vanity on one side, a soaking tub on the other, and a toilet room with a small shower. Very interestingly placed, but a large amount of unused space.
The plan we had was to move the laundry (which was originally installed in the pantry off the kitchen) to the master bathroom, removing the tub and enlarging the shower. This was the largest technical challenge, with rerouting plumbing and electrical.
Laundry in the Pantry? |
Didn't need that wall. |
There was also a linen closet on the wall with the tub. What we didn't know is if the closet was hiding something, since the back wall was six inches out from the other wall.
Who needs a linen closet? |
Oh, that's where it went. |
Remodeling - Main Floor Bathroom Demo
Before |
The main floor bathroom was beige. Tub, shower, toilet, paint, counter, sink, floor all beige. The cabinet was unfinished wood, but apparently the dominant color in 1980 was beige.
Didn't need the toilet, vanity, ... |
or Shower |
Remodeling - Garage Closet
Closet in Garage |
The garage is downstairs and the nature preserve is out the back, so a majority of the time, we will be coming in and out through the garage. So, I decided to build a coat closet in the garage.
The photo shows a door to the left that leads upstairs with a small platform. Before I started construction, the platform ended about 4 feet from the wall. Utilizing some left over packing crates from work, I was able to create a platform and a closet in the corner. The chest freezer will go under the shelf when we move, and the majority of our coats will be able to be put in the closet.
View into the closet. |
Even better, I was able to re-purpose material that was destined for the dump, old flooring from our bathroom, and other materials around the house. The total cost (excluding labor) was less than $10.